The complexity rating assigned to a This rating helps to determine how long it will take for a request to go through the entire procurement process. This is important because a buyer’s performance is evaluated on whether or not they are completing their required tasks on time for their procurements.
is extremely important.Configuration Points:
Complexity ratings are set up on the Procurement Complexity (CMPLX) table. After establishing complexity ratings, you are then able to select a default complexity rating for each Procurement Type in the Complexity field on the Procurement Type tab of the Procurement Type table.
Note:
The complexity number is multiplied by the number of required days to finish each milestone within the procurement to calculate the total number of required days. By establishing the average complexity with a rating of 1.00, the total number of days required will exactly equal the total number of days required to complete each milestone.
A manager can change the complexity rating for a particular procurement within a procurement type by using the Procurements I Manage or Procurements My Team Manages links displayed on the Procurement Management page.